Looks great!
Yes,
I’m looking forwards to getting stuck into the partition. I’ve bought the doors and we had a good look at it all on Wednesday evening.
I can get most of the partition materials in/on the van without too much pain. At least to get it started.
I’d say an important next step is working out materials for the floor and working out staged delivery and how we’re going to manage the materials.
Floor and first partition can be worked on concurrently, as has be pointed out before.
The timber, sheet and insulation I know @tomnewsom will be able to calculate.
The blocks for the floor: we need a count of exactly what we have now, and possibly a bit of measuring of the concrete heights? Although 100mm blocks are probably the only ones available easily, so maybe just go ahead and order?
How much Damp proof course is left?
My approach to materials is that it’s better to waste a bit of money on having a small amount extra, compared with the waste of people’s time running around picking up extras.
We set up a water level before, but I haven’t seen the clear tube for this in ages. Could just buy a length of clear hose? It’s a very useful and accurate way of transferring heights around big areas.