Happy to have a natter about the lighting installation. @joeatkin2 and I had a chat previously and have agreed the electrical approach, the hardest bit is defo the physical installation…
One thing to think about and I’m not sure if it should/could be done at the same time is we need to run round trunking at 90deg to the fittings on the ceiling to pick up the feed cables. From the trunking to the fitting we were thinking of using the 3 core armoured flex or, if we don’t have enough, use standard 3 core flex
I’m still 50/50 for this Thursday as I’m traveling with work but will let you know if/when I’ll be there…
Courty